El Sobrante is unincorporated, so there is no city hall here. Permits, inspections and setback questions all go to the county instead, and that shapes the calendar more than the concrete does.
The parcels are the other half of it. Lots run to an acre and beyond on ground that rises and falls, most are on septic, and some are still on a well, so there are 2 buried systems to find before anything is dug. A slab set over a leach field is a failure that shows up years later, and a mixer that cannot make the last 150 feet turns a 1 day pour into 2.
So the survey comes before the quote. We locate the tank, the field and the well line, plan the concrete clear of all 3, and settle on the visit whether the job is chuted, barrowed or pumped. A drive that a delivery truck shares goes 6 inches over 4 inches of compacted base, and we bring a pump rather than ask a driver to reverse 200 feet blind.